About the project

Client: Confidential
Location: Belgium (Brussels)
Completion: 2018
Total Investment Cost: ca. 65m€

Project description

Implementation of new Vaccine production unit in an existing facility. Increase of capacity from 34 to 56 million doses.

Provided services

Assistance of General contractor Vinci group for commissioning/qualification and document management activities.

Serviced packages

Clean Utilities (Purified Water; Water for Injection, Pure Steam, Compressed Air, NaOH, Biowaste, Process Drain systems).

Process Equipment (Media – buffer prep vessels, media hold vessels, buffer hold vessels, pooling vessels, final filtration, clarification)

Process automation